Dulaney HS - Construction Updates
2025
9-12-25:
- Awaiting final Site and building permit sign off
10-10-25:
- Project has begun construction – Sitework is underway
November Update:
- Site demolition underway
- Sediment and erosion control in progress
- Staging and laydown areas in progress
2026
January Update:
- Sitework ongoing
- Grading and site demolition
- Underground utility installation
- Sediment and erosion control in progress
- Site grading in progress
- Staging site logistics in progress
February Update:
- Underground stormwater and Sand filtration system ongoing
- Site demolition continuing
- Underground Utility work in progress
- Site utilities underway
March Update:
- Site drive lanes and parking underway
- Building pad subgrade underway
- Foundations underway
- Site utilities in progress
- Retaining walls nearing completion
June Update:
- Stormwater management work ongoing
- Transformer and Pad have been set by BGE
- Fencing installation underway
- Curb/Gutter/Sidewalk in progress
- Site utility work ongoing
- Site retaining walls in progress
- Building foundations underway
- Under slab rough-ins in progress
July Update:
- Sitework – grading, utilities, and retaining walls ongoing
- Lower-Level Area A in progress – PE area
- Crane for structural steel being built
- Building footings ongoing
- Underground utilities in progress