Towson HS - Construction Updates
2025
6-20-25:
- Grading and Storm Water Management (SWM) permits have been approved. Building permit pending.
- Site work to start within two weeks.
- On site surveying is ongoing
- Marking of Trees to remain is underway and will be complete by 6/20/25.
- Stake out of major site features will be complete on 6/20/25 for neighbor walkthrough – June 30, 2025 at 6 p.m.
6-30-25:
- Clarification - Walking path at south side of property will remain as a “Dirt Pathway”.
Early July Update:
- Install sediment erosion controls
- Install site security fencing
- Begin forestry work
- Install temporary construction offices
Mid July Update:
- Ongoing sediment and erosion controls installation
- Site security fencing ongoing
- Tree removal ongoing
- Temporary construction facilities ongoing
- Miscellaneous site demolition
Early August Update:
- Sediment and erosion controls and site stabilization ongoing
- Site security fencing ongoing
- Installation of temporary construction facilities ongoing
- Miscellaneous site demolition
- Minor building demolition ongoing
8-7-25:
- The dirt pathway near the bridge by the baseball field will be closed for the duration of construction due to safety concerns.
Late August Update:
- Sediment and erosion controls and site stabilization ongoing
- Miscellaneous site demolition continues
- Underground utility installation
Early October Update:
- Sediment and erosion control and site stabilization ongoing
- Grading and miscellaneous site demolition ongoing
- Underground utility installations ongoing
- Preparations for structural foundations
November Update:
- Site work ongoing
- Grading and miscellaneous site demolition
- Underground utility installation
- Structural foundations in progress
- Retaining wall preparations in progress
2026
January Update:
- Site work ongoing
- Grading and miscellaneous site demolition
- Underground utility installation
- Retaining wall installation begins approximately 1/10 – weather permitting
- Structural foundations in progress
- Slab on grade installation - Earlier start times may occur to take advantage of suitable weather conditions for concrete pours.
- Crane setup and structural steel erection
February Update:
- Sitework – grading, utilities, and retaining wall
- Structure – school addition foundations, slab on grade, and steel erection
- Systems – school addition underground mechanical, electrical, and plumbing
- Stadium renovations – track, turf, and comfort station
March Update:
- Sitework – grading, utilities, and retaining wall in progress
- Structure – school addition slab on grade, suspended slabs, and steel erection under way
- Systems – school addition mechanical, electrical, and plumbing ongoing
- Stadium renovations – track, turf, comfort station, ticket booth, bleachers, and press box progressing
June Update:
- Sitework – grading, utilities, and retaining walls ongoing
- Structure – school addition floor slabs and steel erection ongoing
- Architecture – school addition masonry walls and framing ongoing
- Systems – school addition mechanical, electrical, and plumbing in progress
- Stadium renovations – track, turf, comfort station, ticket booth, bleachers, and press box ongoing
- BGE Project – roadway infrastructure upgrades on Aigburth Rd ongoing
July Update:
- Sitework – grading, utilities, and retaining walls ongoing
- Structure – school addition stairways
- Architecture – school addition interior and exterior walls
- Systems – school addition mechanical, electrical, and plumbing ongoing
- Stadium renovations – track, turf, comfort station, ticket booth, bleachers, and press box ongoing
- BGE Project – roadway infrastructure upgrades on Aigburth Rd ongoing
- Work start and stop times are determined by the contractor as required to achieve the project schedule based on manpower, weather, and on-site trade coordination.