Admin

Towson HS - Construction Updates

2025

6-20-25:

  • Grading and Storm Water Management (SWM) permits have been approved. Building permit pending.
  • Site work to start within two weeks.
  • On site surveying is ongoing
    • Marking of Trees to remain is underway and will be complete by 6/20/25.
    • Stake out of major site features will be complete on 6/20/25 for neighbor walkthrough – June 30, 2025 at 6 p.m.

6-30-25:

  • Clarification - Walking path at south side of property will remain as a “Dirt Pathway”.

Early July Update:

  • Install sediment erosion controls
  • Install site security fencing
  • Begin forestry work
  • Install temporary construction offices

Mid July Update:

  • Ongoing sediment and erosion controls installation
  • Site security fencing ongoing
  • Tree removal ongoing
  • Temporary construction facilities ongoing
  • Miscellaneous site demolition

Early August Update:

  • Sediment and erosion controls and site stabilization ongoing
  • Site security fencing ongoing
  • Installation of temporary construction facilities ongoing
  • Miscellaneous site demolition
  • Minor building demolition ongoing

8-7-25:

  • The dirt pathway near the bridge by the baseball field will be closed for the duration of construction due to safety concerns.

Late August Update:

  • Sediment and erosion controls and site stabilization ongoing
  • Miscellaneous site demolition continues
  • Underground utility installation

Early October Update:

  • Sediment and erosion control and site stabilization ongoing
  • Grading and miscellaneous site demolition ongoing
  • Underground utility installations ongoing 
  • Preparations for structural foundations

November Update:

  • Site work ongoing
    • Grading and miscellaneous site demolition
    • Underground utility installation
  • Structural foundations in progress
  • Retaining wall preparations in progress

2026

January Update:

  • Site work ongoing
    • Grading and miscellaneous site demolition
    • Underground utility installation
  • Retaining wall installation begins approximately 1/10 – weather permitting
  • Structural foundations in progress
  • Slab on grade installation - Earlier start times may occur to take advantage of suitable weather conditions for concrete pours.
  • Crane setup and structural steel erection

February Update:

  • Sitework – grading, utilities, and retaining wall 
  • Structure – school addition foundations, slab on grade, and steel erection
  • Systems – school addition underground mechanical, electrical, and plumbing
  • Stadium renovations – track, turf, and comfort station

March Update:

  • Sitework – grading, utilities, and retaining wall in progress
  • Structure – school addition slab on grade, suspended slabs, and steel erection under way
  • Systems – school addition mechanical, electrical, and plumbing ongoing
  • Stadium renovations – track, turf, comfort station, ticket booth, bleachers, and press box progressing

June Update:

  • Sitework – grading, utilities, and retaining walls ongoing
  • Structure – school addition floor slabs and steel erection ongoing
  • Architecture – school addition masonry walls and framing ongoing  
  • Systems – school addition mechanical, electrical, and plumbing in progress
  • Stadium renovations – track, turf, comfort station, ticket booth, bleachers, and press box ongoing 
  • BGE Project – roadway infrastructure upgrades on Aigburth Rd ongoing

July Update:

  • Sitework – grading, utilities, and retaining walls ongoing
  • Structure – school addition stairways 
  • Architecture – school addition interior and exterior walls 
  • Systems – school addition mechanical, electrical, and plumbing ongoing
  • Stadium renovations – track, turf, comfort station, ticket booth, bleachers, and press box ongoing 
  • BGE Project – roadway infrastructure upgrades on Aigburth Rd ongoing
  • Work start and stop times are determined by the contractor as required to achieve the project schedule based on manpower, weather, and on-site trade coordination.
Website by SchoolMessenger Presence. © 2026 SchoolMessenger Corporation. All rights reserved.